PREPERATION OF BED

                       PREPARATION OF BED



Material used for preparation of bed :
1 . Square tubes
2 .Plywood
3 .Welding rods
4 . colour
5 . Touchwood
6 . Primer ( Redoxide )
7 . Brushes

8 . Thinner




PROCESSES PERFORMED DURING BED PREPARATION :
1 . Cutting
2 . Welding
3 . Grinding
4 . Painting
TABLE :  COST ESTIMATION
Material Cost :
Sr. no
Product name
Total products
Rate
Cost (Rs)
1
2* 1 tube
18 ft
19.5/ft
351
2
¾ * 3/4 tube
12.1 ft
8/ft
96.8
3
1.5 * 1.5 tube
7 ft
25/ft
175
4
Plywood
2.42*5.74 ft2
55/ft2
764
5
Welding rod
25
2.5/rod
62.5
6
colour
250 ml
250/1000ml
62.5
7
Touchwood
250 ml
300/1000ml
75
8
Primer
250 ml
180/1000ml
45
9
Brush
2 (2 inch)
50
100
10
Thinner
250 ml
140/1000ml
35


Labour cost is 15% of total material cost
Labour cost = 1767 * 0.15
                       =Rs  265
Electricity cost is 10% of total material cost
Electricity cost = 1767 * 0.10
                             = Rs 178
Total cost = 1767+265+178
                   =Rs 2210